Anticipated adverse weather days for your site

Twelve monthly numbers, in the layout federal and state contracts use, from the nearest NOAA station with a complete record, plus the year-by-year table behind them, for a schedule, a bid or a delay claim.

What you get for one site

The layout, with Houston, TX as an example

Monthly anticipated adverse weather days, rain of 0.10 in or more, 2006–2025, NOAA GHCN-Daily station Houston-Westbury (USC00414325, 8.8 km from the city centre).

Work weekJANFEBMARAPRMAYJUNJULAUGSEPOCTNOVDECYear
Five-day work week43334554443446
Seven-day work week64446676655564

Download the sample PDF (three pages: the schedule, then the counts of every year behind each row) · sample CSV

How the numbers are made

The station is the best-ranked NOAA GHCN-Daily station within 30 km of the site whose precipitation record covers at least 90 % of the days of the period, National Weather Service first-order stations first. The period is the last 20 complete years by default (10, 15 or 30 on request). For each calendar month the days that meet the rule are counted in every year: on all days for the seven-day row, and on Monday to Friday only for the five-day row (the weekday days are counted, not the seven-day number times 5/7). A month with less than 80 % of its days reported is left out of that year, and a partly reported month is scaled to the full month. Each number in the schedule is the mean over the years, rounded to a whole day (a half rounds up). Public holidays are not taken out. Where no NOAA station within 30 km has a complete record, the report says so and uses gridded daily data at the site instead, named as such.

Where this layout comes from

US Army Corps of Engineers contracts carry a clause on time extensions for unusually severe weather (from regulation ER 415-1-15) with a schedule of monthly anticipated adverse weather delays "based on National Oceanic and Atmospheric Administration (NOAA) or similar data for the project location". Many state and owner specifications use a similar monthly table, stated for a five-day or a seven-day work week. The table here follows that layout. Your contract sets the rule, the work week, and how much of a work day the weather must stop for a day to count: read the clause, and use the numbers as data, not as advice.

Five-day schedules in 30 US cities

Anticipated adverse weather days, five-day work week, rain of 0.10 in (2.5 mm) or more, 2006–2025, NOAA GHCN-Daily station nearest the city centre. Last column: the seven-day total. A site away from the centre can use a different station: build the table for your own site.

City JanFebMarAprMayJunJulAugSepOctNovDec 5-day7-day
Phoenix, AZ1110001210121014
Los Angeles, CA3221000001131319
San Diego, CA2221000001131217
San Francisco, CA5553100002352940
Denver, CO1123533322112736
Washington, DC4444655443445171
Jacksonville, FL3333477753335171
Chicago, IL2345654535334867
Indianapolis, IN4456655435455675
Louisville, KY4556665435455879
Boston, MA4555555444455576
Baltimore, MD4444555444445172
Detroit, MI3245545444334664
Charlotte, NC4554545543445270
Albuquerque, NM1111113221111622
Las Vegas, NV11100001111188
New York, NY4554556544455677
Columbus, OH4556666445456081
Oklahoma City, OK2233643333223648
Portland, OR9897531136997096
Philadelphia, PA4544465444455372
Memphis, TN4565545434455472
Nashville, TN4565555445455779
Austin, TX3233532133223242
Dallas, TX3343532233333752
El Paso, TX1100113321111520
Houston, TX4333455444344664
San Antonio, TX2122322233222636
Seattle, WA8675321135875676
Milwaukee, WI3345554435334767

During the project

The weather-day tool counts the actual weather days since the project start with the same rule, month by month, and can email the count on the 5th of each month.

The same station networks feed EPW.tools' hourly EnergyPlus weather files (EPW) and design conditions for the building itself.

Frequently asked questions

What are anticipated adverse weather days?

The number of days in each month on which the weather at the site normally meets the contract's rule for an adverse weather day, from the station record. Contracts that use them grant time only for the days above that number.

Five-day or seven-day work week?

Both rows are in the report. The five-day row counts only the adverse days that fell on Monday to Friday; the seven-day row counts every day. Use the one your contract or schedule states.

Which station is used?

The best-ranked NOAA GHCN-Daily station within 30 km of the site with precipitation on at least 90 % of the days, National Weather Service first-order stations first. The report names it by number.

Why 20 years?

A longer record keeps one wet or dry year from moving the schedule. You can choose 10, 15, 20 or 30 years.

What does it cost?

The table on screen and the CSV are free with a free account. The PDF report costs 1 credit.

Is this legal advice?

No. The report records the data and the method. How days are counted, and whether a day counts as a delay, is set by the contract.

Build the table for your site

Free to try, no credit card.

Build my table →